Adams Road & Simcoe Boulevard AODA Ramp

Share Adams Road & Simcoe Boulevard AODA Ramp on Facebook Share Adams Road & Simcoe Boulevard AODA Ramp on X (formerly Twitter) Share Adams Road & Simcoe Boulevard AODA Ramp on Linkedin Email Adams Road & Simcoe Boulevard AODA Ramp link

Consultation has concluded

Thank you to everyone who was involved in the accessible ramp by Adams Rd and Simcoe Blvd. The project is now complete and we are excited to now have an improved space that is AODA (Accessibility for Ontarians with Disabilities Act) compliant and accessible to all.

Why did we make these improvements?

The Town has a commitment to continuous improvement and to comply with accessibility guidelines. Making progress to an accessible Innisfil is a strategic priority as identified in the Community Strategic Plan. Improving accessibility benefits everyone who accesses Town goods, services and facilities and is a component to making Innisfil a diverse and inclusive community that strives to improve the quality of life for all persons.

When an exterior path of travel is being redeveloped, the AODA requires that it be done in an accessible manner subject to some exceptions. Since the existing staircase has exceeded its useful life, it requires a full replacement. The pathway serves a functional purpose by allowing pedestrians to walk from one road to the other, the AODA requires that a ramp be constructed at this location given the difference in elevation between the two roadways.

This section of roadway was identified in the Town's Trails Master Plan (TMP) as a connection for users of active transportation, including but not limited to cyclists and pedestrians. The TMP identifies these roadway sections of Lakelands Ave, Adams Rd and Simcoe Blvd as an area that will receive sharrows to better facilitate cycling activities and connections to downtown Alcona for all users.

In order to make this area accessible to all pedestrians, the ramp now:

  • Improves the condition and safety of pedestrian access between Adams Rd and Simcoe Blvd.
  • Complies with the AODA;
  • Complies with the Town of Innisfil's Community Strategic Plan which highlights that improving accessibility within the Town of Innisfil is a strategic priority; and
  • Makes the community connections provided in the Town's Trails Master Plan.


Thank you to everyone who was involved in the accessible ramp by Adams Rd and Simcoe Blvd. The project is now complete and we are excited to now have an improved space that is AODA (Accessibility for Ontarians with Disabilities Act) compliant and accessible to all.

Why did we make these improvements?

The Town has a commitment to continuous improvement and to comply with accessibility guidelines. Making progress to an accessible Innisfil is a strategic priority as identified in the Community Strategic Plan. Improving accessibility benefits everyone who accesses Town goods, services and facilities and is a component to making Innisfil a diverse and inclusive community that strives to improve the quality of life for all persons.

When an exterior path of travel is being redeveloped, the AODA requires that it be done in an accessible manner subject to some exceptions. Since the existing staircase has exceeded its useful life, it requires a full replacement. The pathway serves a functional purpose by allowing pedestrians to walk from one road to the other, the AODA requires that a ramp be constructed at this location given the difference in elevation between the two roadways.

This section of roadway was identified in the Town's Trails Master Plan (TMP) as a connection for users of active transportation, including but not limited to cyclists and pedestrians. The TMP identifies these roadway sections of Lakelands Ave, Adams Rd and Simcoe Blvd as an area that will receive sharrows to better facilitate cycling activities and connections to downtown Alcona for all users.

In order to make this area accessible to all pedestrians, the ramp now:

  • Improves the condition and safety of pedestrian access between Adams Rd and Simcoe Blvd.
  • Complies with the AODA;
  • Complies with the Town of Innisfil's Community Strategic Plan which highlights that improving accessibility within the Town of Innisfil is a strategic priority; and
  • Makes the community connections provided in the Town's Trails Master Plan.


Consultation has concluded
  • Construction Schedule Extended

    Share Construction Schedule Extended on Facebook Share Construction Schedule Extended on X (formerly Twitter) Share Construction Schedule Extended on Linkedin Email Construction Schedule Extended link
    supporting image

    Due to COVID-19, the expected opening of the ramp is anticipated to be delayed until October 22nd, 2020. Though the bulk of construction will be complete by the original scheduled date of October 5th, 2020 - the manufacturing of the helical piles for the ramp foundation as well as the railing system on the ramp has taken longer than expected. The Town is unable to safely open the ramp for use until the railings have arrived and are installed.

    Due to COVID-19, the expected opening of the ramp is anticipated to be delayed until October 22nd, 2020. Though the bulk of construction will be complete by the original scheduled date of October 5th, 2020 - the manufacturing of the helical piles for the ramp foundation as well as the railing system on the ramp has taken longer than expected. The Town is unable to safely open the ramp for use until the railings have arrived and are installed.

    Consultation has concluded
  • Helical Piles are Being Installed

    Share Helical Piles are Being Installed on Facebook Share Helical Piles are Being Installed on X (formerly Twitter) Share Helical Piles are Being Installed on Linkedin Email Helical Piles are Being Installed link
    supporting image

    What are Helical Piles?

    Helical piles, also referred to as screw piles is an anchoring system used for building foundations. Helical piles are usually made out of galvanized steel to avoid corrosion. Helical Piles are used in a wide range of construction projects as they are easy to install, require little to no excavation, and have a minimal impact to the environment. Helical piles are installed with a large auguring machine and set to a certain torque based on the type of soil in the area.

    Helical Piles in this Project

    The ramp will be using 26 helical piles for its foundation. The helical piles being installed are made out of Galvanized Steel to avoid corrosion and provide long-term structural support.

    What are Helical Piles?

    Helical piles, also referred to as screw piles is an anchoring system used for building foundations. Helical piles are usually made out of galvanized steel to avoid corrosion. Helical Piles are used in a wide range of construction projects as they are easy to install, require little to no excavation, and have a minimal impact to the environment. Helical piles are installed with a large auguring machine and set to a certain torque based on the type of soil in the area.

    Helical Piles in this Project

    The ramp will be using 26 helical piles for its foundation. The helical piles being installed are made out of Galvanized Steel to avoid corrosion and provide long-term structural support.

    Consultation has concluded
  • Construction of the AODA Ramp has Started!

    Share Construction of the AODA Ramp has Started! on Facebook Share Construction of the AODA Ramp has Started! on X (formerly Twitter) Share Construction of the AODA Ramp has Started! on Linkedin Email Construction of the AODA Ramp has Started! link
    supporting image

    Construction of the Simcoe Boulevard & Adams Road AODA Ramp has finally begun. The Town has long awaited this project and is excited that it has started. The Town would like to thank all residents and users of the existing staircase for their feedback and thoughts over the past few years as we designed a solution to make these road ends accessible to everyone.

    The road ends is expected to remain closed until construction has completed which is anticipated to be on October 5th, 2020.

    Thank you for understanding.

    Construction of the Simcoe Boulevard & Adams Road AODA Ramp has finally begun. The Town has long awaited this project and is excited that it has started. The Town would like to thank all residents and users of the existing staircase for their feedback and thoughts over the past few years as we designed a solution to make these road ends accessible to everyone.

    The road ends is expected to remain closed until construction has completed which is anticipated to be on October 5th, 2020.

    Thank you for understanding.

    Consultation has concluded
  • Adams Road & Simcoe Boulevard AODA Ramp Construction Status Updates

    Share Adams Road & Simcoe Boulevard AODA Ramp Construction Status Updates on Facebook Share Adams Road & Simcoe Boulevard AODA Ramp Construction Status Updates on X (formerly Twitter) Share Adams Road & Simcoe Boulevard AODA Ramp Construction Status Updates on Linkedin Email Adams Road & Simcoe Boulevard AODA Ramp Construction Status Updates link

    Check this section weekly to view construction status updates on the AODA Ramp.

    Check this section weekly to view construction status updates on the AODA Ramp.

    Consultation has concluded