September 2025

Project Kick-off and Background Studies

During this phase, the consultant, R.J. Burnside & Associates:  

  • Delivered the Project Management Plan
  • Reviewed the study area, issues to be considered, and relevant projects
  • Identified stakeholders and others who may have interest in the project
September 2026

TAC Meeting #1

The first TAC meeting presented the study purpose, reviewed the four preliminary alternatives and the evaluation criteria, and gathered feedback from participants.

January 2026

TAC Meeting #2

The second TAC meeting will review and discuss issues and concerns in the study area and review draft Public Open House #1 materials.

February 2027

Public Open House #1

The first Public Open House will be held at Town Hall. It will be in person, and materials and a comment form will be posted on this webpage following the event.

The purpose is to outline the study, key findings, alternative solutions, evaluation leading to the preferred solution, present conceptual plans, and discuss potential property impacts.

July 2027

TAC Meeting #3

The third TAC meeting will obtain input on design alternatives and review and discuss draft Public Open House #2 materials.

September 2027

Public Open House #2

The second Public Open House will update the public on project activities and key studies, the alternative design solutions evaluated for the preferred solution, and the preferred alternative design.

January 2028

TAC Meeting #4

The final TAC meeting will review and discuss the final draft of the Environmental Study Report.

August 2028

Notice of Study Completion

In this final phase, a Final Study Report, Notice of Completion, and Environmental Study Report will be published for a 30-day public review and comment period.