Reive Boulevard

Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

Project background:

The Town is giving some TLC to Reive Blvd from Hwy 89 to the 4th line. These updates include the installation of a bridge in replacement of double culverts. A retaining wall will also be replaced for a culvert on the 3rd Line as well. In addition, we'll be repaving from the end of the MTO construction work on Hwy 89 to the 4th Line.

The works to be completed in this project were recommended in the Town’s biennial bridge inspections as well as in the recent Final Engineer’s Report on the South Innisfil Creek Drain 2019 Improvement. The report recommended changes to improve the elevation, alignment, and hydraulic capacity of structure to help prevent upstream flooding in the market garden agricultural area. The current construction addresses these concerns. In addition, this stretch of Reive Boulevard was identified as requiring resurfacing in the 2018 Roads Needs Study and roadside safety improvements were identified through both the 2018 Roads Needs Study and the detailed design. The resurfacing and roadside safety upgrade works were incorporated into the design for this project and are being completed as part of this construction contract.

How will this affect residents?

There will be road closures in effect at varying times during the project and construction noise during the day. Advance notice will be given to residents as to detour routes to take.

If you have any questions about the project, please contact Bobbi-Jo Duncan, Capital Project Manager at bduncan@innisfil.ca

Project background:

The Town is giving some TLC to Reive Blvd from Hwy 89 to the 4th line. These updates include the installation of a bridge in replacement of double culverts. A retaining wall will also be replaced for a culvert on the 3rd Line as well. In addition, we'll be repaving from the end of the MTO construction work on Hwy 89 to the 4th Line.

The works to be completed in this project were recommended in the Town’s biennial bridge inspections as well as in the recent Final Engineer’s Report on the South Innisfil Creek Drain 2019 Improvement. The report recommended changes to improve the elevation, alignment, and hydraulic capacity of structure to help prevent upstream flooding in the market garden agricultural area. The current construction addresses these concerns. In addition, this stretch of Reive Boulevard was identified as requiring resurfacing in the 2018 Roads Needs Study and roadside safety improvements were identified through both the 2018 Roads Needs Study and the detailed design. The resurfacing and roadside safety upgrade works were incorporated into the design for this project and are being completed as part of this construction contract.

How will this affect residents?

There will be road closures in effect at varying times during the project and construction noise during the day. Advance notice will be given to residents as to detour routes to take.

If you have any questions about the project, please contact Bobbi-Jo Duncan, Capital Project Manager at bduncan@innisfil.ca

Consultation has concluded
  • Reive Boulevard 2021 construction resuming

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    CLOSED: This discussion has concluded.

    The construction on Reive Boulevard is scheduled to resume the week of May 3, 2021. The contractor will be continuing the construction of the bridge and the roadwork between 2nd Line and Hwy 89. They will also complete the paving of the top course of asphalt from 4th Line to Hwy 89 this summer. The project is estimated to be completed in June 2021.

  • Closure update - August 11, 2020

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    CLOSED: This discussion has concluded.

    Road closures in place between 3rd line and 4th line from July 27, 2020 to December 7, 2020.

    A road closure will be in place between the Innisfil Creek Golf Course and the KOA Campground from August 13, 2020 to December 7, 2020 for culvert replacement and bridge erection. During this time, access to the Innisfil Creek Golf Course will be maintained using 10 Sideroad and the 2nd Line. Access to the KOA Campground will be maintained from Hwy 89 and Reive Blvd. Please refer to the Documents section for further information.