Lockhart Road Reconstruction and Servicing
Project Status
The Town of Innisfil is preparing to undertake the reconstruction of Lockhart Road and 25th Sideroad. The Lockhart Road reconstruction limits will extend 200m west of 25th Sideroad and 1400m east of 25th Sideroad ending at Lake Simcoe. The 25th Sideroad reconstruction limits will extend 180m north of Lockhart Road and 430m south of Lockhart Road.
The project scope will include full depth road reconstruction, drainage improvements, new watermain and sewer installations, new traffic signals and turning lanes (Intersection of Lockhart Road & 25th Sideroad) and a road end parkette at the end of Lockhart Road. Utility relocations are required to facilitate the proposed works, relocations are scheduled to start March 2023. Construction work will follow the utility relocations and is anticipated to start early fall 2023.
Engagement Updates
The Town of Innisfil and InnServices held a Public Open House for the Lockhart Road East Reconstruction Project and the Sandy Cove Sewage Pumping Station Environmental Assessment on March 23, 2023 at The Wheel in Sandycove Acres. We thank everyone who took the time to provide feedback on these projects by attending the open house or filling out an online comment sheet.
For additional information on the Sandy Cove SPS EA, please visit InnService's project webpage.
Project Background
The need to improve Lockhart Road was identified in the Town's 2018 Transportation Master Plan. Road and infrastructure improvement projects like this one are essential for keeping our community safe and connected.
The project's first phase involved reconstruction on Lockhart Road from 20th Sideroad to 25th Sideroad. The project has now entered the second phase, which involves reconstructing Lockhart Road from 25th Sideroad to Lake Simcoe.
Phase 2 Project Features
The proposed roadway improvements include:
- Expansion of the Lockhart Road and 25th Sideroad intersection, including the addition of traffic lights
- Watermain installation from 25th Sideroad to the west leg of Crescent Road
- Road reconstruction of Lockhart Road from 25th Sideroad to the lake, including the addition of active transportation lanes
- The creation of a parkette at the lake
- Utility relocations
- Drainage improvements
Timeline
We expect the construction to begin in the Fall of 2023, and the work will take 2 to 3 years. The Town is still working to confirm construction timelines, but we expect it to progress as follows:
- Tree Clearing - Complete
- Utility Relocations – Spring/Summer 2023
- Drainage Improvements - Fall 2023
- Watermain Installation & Road Reconstruction – Spring 2024
- Parkette creation – 2024
- Intersection expansion and signalization – 2024
If you have questions, you can contact us by calling 705-436-3710 or 1-888-436-3710 (toll free), or by emailing inquiry@innisfil.ca. You can also submit an inquiry through our online form.